More demo, poured concrete and framing, oh my!
Posted August 8, 2019
The past two weeks have been very busy on site as construction ramps back up!
- Openings are cut for the elevator shaft and stairs all the way to the roof
- Basement storage pit opening is cut and framed out
- Concrete for part of the brewery floor is poured
- First floor brewery bathrooms, bar and storage is framed out

It’s all starting to come together, little by little! Stay tuned for more updates!